Power and Steam Generation Facilities

Titan Chemicals owns and operates two co-generation plants, one each at its Pasir Gudang and Tanjung Langsat sites. These co-generation plants have a combined installed power capacity of 92 MW, which is sufficient to meet the power requirements of Titan Chemicals production facilities at peak usage.  The co-generation plants are powered by a mixture of natural gas sourced from Petronas Gas Sdn Bhd ("Petronas Gas"), and fuel oil and gas from Titan Chemicals two crackers

The following table sets forth the co-generation capacity at each of Titan Chemicals power plants:

. Pasir Gudang Tanjung Langsat .
Utility Co-generation plant 1 Steam turbine generator Co-generation plant 2 Steam turbine generator Total
Power (MW)

44.0

8.0

22.0

18.0

92.0

Steam (MT/Hr)

160.0

-

135.0

-

295.0

Natural Gas (1,000 SM3/Hr)

13.3

NA

6.6

NA

19.9

Fuel Oil (MT/Hr)

2.6

NA

2.6

NA

5.2